In January of 1994, the
conservation and alteration for adaptive re-use of the Duff Baby House
took place in Sandwich, Ontario. Built in1798, it is one of the oldest
structures in Ontario still on its' original site. It had been used
continuously as a residence until its' acquisition, in 1987, by the
Ontario Heritage Foundation. From 1987, the building served as the
regional office of the Ministry of Culture, Tourism & Recreation.
Architectural investigation
of this significant building began in 1994, with the exact scope of work
undetermined at the outset. Operating under a fixed budget of $650,000,
the extent of required repairs and cost effective solutions were
established as the investigation proceeded. Initially, the existing
cement/asbestos shingle siding was removed by a specialist contractor to
ensure minimal damage to the two-hundred year old weatherboards beneath.
At this point, a timber
engineering consultant was engaged to provide information regarding
timber species, condition and structural adequacy. It was determined
that most of the sill plate had deteriorated and required replacement.
In order to facilitate this work, the house was shored and lifted
hydraulically approximately 3 inches to allow the original sill to be
lifted and replaced with a new sill to match. Foundation repair was
completed prior to the sill replacement. Original mortar was removed by
hand and the walls were re-pointed with a lime based mix.
The majority of the windows
dated from 1798 and these were removed, restored and reinstalled. The
removal of the siding revealed the trace of a door pediment that was
taken down in the 1830's to allow the fitting of the first full width
porch. This original detail was recreated during restoration.
Owner:Ontario Heritage Foundation
Architect: George Robb Architect
Peter Stewart (project architect)
Donald Scott, Stephen Marshall
Timber Specialist:James Knight, P.Eng.
Structural Engineer:Hanna, Gobrial & Spencer
Mechanical Engineer: MGG Engineering
General Contractor:Interthon Construction Ltd.
Building Area:4,500 sf
Construction Cost:$650,000.00
Completion:March 1995